Data Center Zoning Compliance Permit Requirements (in order)

  1. Land is zoned industrial.
  2. Special Exception Review to evaluate impacts of industrial use impacts on adjacent residential properties (expected Land Use Board hearing date 7/1/26)
    1. Topics to be considered include traffic, access, and parking; pedestrian facilities; impacts on utility services; impacts on new structures and their relationship to adjoining properties; natural resource protections; landscaping; noise, vibration, and outdoor lighting; signage; hours of operation; and, visual impacts and effect on the character of the neighborhood.
    2. The Land Use Board may consider any other relevant circumstances related to the industrial use's impact on the adjacent residential properties.
  3. Submittal of Zoning Compliance Permit application & Building Permit application.
    1. This is when the Planning Dept. will review for compliance with zoning regulations, including provision of 100% renewable energy and recycling and e-waste.
Share Data Center Zoning Compliance Permit Requirements (in order) on Facebook Share Data Center Zoning Compliance Permit Requirements (in order) on Twitter Share Data Center Zoning Compliance Permit Requirements (in order) on Linkedin Email Data Center Zoning Compliance Permit Requirements (in order) link