Phase 2 (RSID 8490) Cost Estimates
EPA Grant | Water RSID Bond | Sewer RSID Bond | Total | |
Administrative Incidental Costs | $ - | $ 7,690 | $ 7,690 | $ 15,380 |
Revolving Fund Deposit | $ - | $ 159,450 | $ 118,050 | $ 277,500 |
Interim Interest | $ - | $ 136,367 | $ 101,013 | $ 237,380 |
Bond Counsel and Related Costs | $ - | $ 35,000 | $ 35,000 | $ 70,000 |
Engineering (Design) | $ - | $ 250,000 | $ 100,000 | $ 350,000 |
Engineering (Construction Admin) | $ - | $ 300,000 | $ 130,000 | $ 430,000 |
Construction (Contractor) | $ 1,750,000 | $ 2,100,000 | $ 1,700,000 | $ 5,550,000 |
Contingency | $ - | $ 200,493 | $ 169,247 | $ 369,740 |
TOTAL COSTS | $1,750,000 | $ 3,189,000 | $ 2,361,000 | $ 7,300,000 |
Share Phase 2 (RSID 8490) Cost Estimates on Facebook
Share Phase 2 (RSID 8490) Cost Estimates on X (formerly Twitter)
Share Phase 2 (RSID 8490) Cost Estimates on Linkedin
Email Phase 2 (RSID 8490) Cost Estimates link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends