Data Center Interim Zoning

Share Data Center Interim Zoning on Facebook Share Data Center Interim Zoning on X (formerly Twitter) Share Data Center Interim Zoning on Linkedin Email Data Center Interim Zoning link

Update 11/12/2026:

The county commissioners approved the Data Center Interim Zoning study and directed staff to proceed with the study's recommended course of action at their Nov. 12 public hearing meeting. The action items include:

  • Develop updated countywide zoning regulations to address identifiable data center land use impacts, with final regulations to be completed after the 2027 Montana Legislative Session so that any statutory changes can be addressed.
  • Work with the County's legislative delegation, other local governments and departments, and interested organizations on appropriate regulations and legislation addressing data center impacts that cannot be adequately addressed through local zoning.
  • Continue Missoula County's participation in NorthWestern Energy's Large New Load Tariff proceeding before the Montana Public Service Commission, and other appropriate utility proceedings, to help protect existing utility customers from inappropriate cost-shifting and stranded-asset risk associated with large new electrical loads.




Project Description

On July 9, the Missoula County commissioners adopted a countywide one-year moratorium on new or expanded data centers outside of the City limits. This temporary moratorium followed substantial public engagement and allows staff time to evaluate the impacts of data centers and determine the best way to regulate them to protect public health, safety and the natural environment.

The moratorium was adopted through interim zoning, which is used when an emergency situation exists. As required by law, the County initiated a study on July 10 to verify the circumstances of the emergency and identify potential options to address it.

County staff have completed a draft of this study and will present it to the public in late October and to the Missoula County Consolidated Land Use Board and the Board of County Commissioners meetings in November. This page is intended to invite feedback from the public on data center impacts and ways to possibly reduce or eliminate those impacts.

As a relatively new use on our landscape, data centers can potentially create significant adverse impacts that the current Missoula County Zoning Regulations do not adequately address. Some examples of these impacts include substantial energy consumption, water quantity and quality impacts, air quality impacts, heat, noise and vibration, among others. The moratorium allows time for staff to research data centers and determine what options are available for preventing or mitigating adverse impacts.

The moratorium is effective for one year unless replaced by new zoning regulations. The expiration date of the moratorium is July 8, 2027. The commissioners may choose to extend the moratorium for a second year, after another legally advertised public hearing.


Click here to read answers to frequently asked questions.


Anticipated timeline

Tuesday, Oct. 27. 6 p.m.: Data Center study presentation

  • In-person location: 1101 South Ave W, Missoula County Fairgrounds, Home Arts Building (virtual option not available)

Wednesday, Nov. 4, 6 p.m.: Presentation to the Missoula County Consolidated Land Use Board

  • In-person location: 200 W. Broadway, Missoula County Courthouse, Sophie Moiese Room
  • Virtual option: Residents can attend the meeting via Microsoft Teams. To join the meeting on your device, follow the links on the agenda that will be published on the Consolidated Land Use Board page.

Thursday, Nov. 12, 2 p.m.: Presentation at the Missoula County commissioners’ public hearing meeting

  • In-person location: 200 W. Broadway, Missoula County Courthouse Annex, Sophie Moiese Room
  • Virtual option: Residents can attend the meeting via Microsoft Teams. To join the call on your phone, call 406-272-4824, Conference ID 467 457 758#. To join the meeting on your device, follow the links on the agenda that will be published online.

More details will be published on this page as the project evolves.


Public comment

Let us know what you think by logging in or creating an account and submitting your comment below. Follow this project on the right-hand side of this page to be emailed when there are updates.

Update 11/12/2026:

The county commissioners approved the Data Center Interim Zoning study and directed staff to proceed with the study's recommended course of action at their Nov. 12 public hearing meeting. The action items include:

  • Develop updated countywide zoning regulations to address identifiable data center land use impacts, with final regulations to be completed after the 2027 Montana Legislative Session so that any statutory changes can be addressed.
  • Work with the County's legislative delegation, other local governments and departments, and interested organizations on appropriate regulations and legislation addressing data center impacts that cannot be adequately addressed through local zoning.
  • Continue Missoula County's participation in NorthWestern Energy's Large New Load Tariff proceeding before the Montana Public Service Commission, and other appropriate utility proceedings, to help protect existing utility customers from inappropriate cost-shifting and stranded-asset risk associated with large new electrical loads.




Project Description

On July 9, the Missoula County commissioners adopted a countywide one-year moratorium on new or expanded data centers outside of the City limits. This temporary moratorium followed substantial public engagement and allows staff time to evaluate the impacts of data centers and determine the best way to regulate them to protect public health, safety and the natural environment.

The moratorium was adopted through interim zoning, which is used when an emergency situation exists. As required by law, the County initiated a study on July 10 to verify the circumstances of the emergency and identify potential options to address it.

County staff have completed a draft of this study and will present it to the public in late October and to the Missoula County Consolidated Land Use Board and the Board of County Commissioners meetings in November. This page is intended to invite feedback from the public on data center impacts and ways to possibly reduce or eliminate those impacts.

As a relatively new use on our landscape, data centers can potentially create significant adverse impacts that the current Missoula County Zoning Regulations do not adequately address. Some examples of these impacts include substantial energy consumption, water quantity and quality impacts, air quality impacts, heat, noise and vibration, among others. The moratorium allows time for staff to research data centers and determine what options are available for preventing or mitigating adverse impacts.

The moratorium is effective for one year unless replaced by new zoning regulations. The expiration date of the moratorium is July 8, 2027. The commissioners may choose to extend the moratorium for a second year, after another legally advertised public hearing.


Click here to read answers to frequently asked questions.


Anticipated timeline

Tuesday, Oct. 27. 6 p.m.: Data Center study presentation

  • In-person location: 1101 South Ave W, Missoula County Fairgrounds, Home Arts Building (virtual option not available)

Wednesday, Nov. 4, 6 p.m.: Presentation to the Missoula County Consolidated Land Use Board

  • In-person location: 200 W. Broadway, Missoula County Courthouse, Sophie Moiese Room
  • Virtual option: Residents can attend the meeting via Microsoft Teams. To join the meeting on your device, follow the links on the agenda that will be published on the Consolidated Land Use Board page.

Thursday, Nov. 12, 2 p.m.: Presentation at the Missoula County commissioners’ public hearing meeting

  • In-person location: 200 W. Broadway, Missoula County Courthouse Annex, Sophie Moiese Room
  • Virtual option: Residents can attend the meeting via Microsoft Teams. To join the call on your phone, call 406-272-4824, Conference ID 467 457 758#. To join the meeting on your device, follow the links on the agenda that will be published online.

More details will be published on this page as the project evolves.


Public comment

Let us know what you think by logging in or creating an account and submitting your comment below. Follow this project on the right-hand side of this page to be emailed when there are updates.

Let us know what you think by logging in or creating an account and submitting your comment below.

Staff do not respond to comments submitted here. If you have a question you would like answered, submit it on the Questions tab.

You need to be signed in to comment in this Guest Book.

You need to be signed in to comment in this Guest Book. Click here to Sign In or Register to get involved

MEC cannot supply the electricity we are already consuming and added peak hour surcharges to offset the costs to purchase additional electricity from Bonneville. Data centers use exorbitant amounts of electricity which will result in higher costs to the current customers and likely expansion of peak usage hours.
Water is already scarce and we are seeing routine and longer periods of drought. Data centers will exacerbate that problem and draw down our basins.
Please correct the zoning so that these centers can never call Montana home.

jmicklitz 15 days ago

It is clearly in the best interest of the citizens of this community to extend this moratorium. Data Centers consume far too much and give us far too little.

Nobody wants these damn things near their home. Nobody wants these things near their rivers.
Data Centers create 0 jobs. They help 0 people.
Nobody likes this. Nobody wants this.

Eli Redeker 16 days ago

The citizens of the Missoula area and surrounding towns cannot be more clear: we do not want these data centers anywhere near us. We have provided evidence, personal opinions, anecdotes, stories, and scientific studies all supporting why we do not want these data centers. We have done our part. Now please do yours and extend this moratorium for as long as possible. Thank you.

B. 18 days ago

Nobody wants these anywhere near our precious resources. The impact on our environment and the potential rise in costs for the consumer makes it seem like a very bad idea. Not to mention the noise and light pollution affect wildlife and their circadian rhythms.
I know 19 years from now we will learn that they also cause cancer. Absolutely not.

indigosky44 21 days ago

I appreciate the County’s Data Center Zoning Study with its comprehensive explanation of data centers, their characteristics, and impacts. I agree with the County’s conclusion that the potential impacts of data center development substantiate the emergency underlying the interim zoning and warrant additional action. I agree with the study’s recommendation that there be targeted, thorough, and protective zoning regulations addressing identifiable environmental and social impacts of data centers.
Data centers will be the subject of extensive legislation during the upcoming session, and it is appropriate to wait for the legislative outcomes and then extend the data center moratorium for another year pending development of appropriate County zoning regulations for data centers.
I appreciate the Climate Context in the study, stating that “Climate change is a significant threat to human and ecosystem health and well-being.” Unregulated data center development can greatly increase the use of fossil fuels for electricity generation, unacceptably increasing the climate degradation that is already underway.
Missoula County zoning regulations for data centers should:
1. Specify maximum size; for example, 20 MW.
2. Require that the data center either a) Supply 100% of its energy use with its own renewable energy or, b) Offset 100% of its energy use by purchasing new, renewable energy that produces the same number of Megawatt-hours as those used by the facility in a year. For example, a 20 MW installation operating continuously 24 hours a day consumes 175,200 Megawatt-hours (MWh) of energy annually. A 20 MW data center in Missoula County should be required to purchase new, renewable energy that would supply 175,200 Megawatt-hours annually.
3. Require backup generation be supplied by LDES battery instead of diesel or gas-powered generation. For example, a redox flow LDES battery can be powered up immediately if there is a loss of system electricity and is less expensive, in the long run, than fossil-fueled backup generation.
4. Require cooling by a closed loop system; prohibit the use of evaporative cooling
5. Prohibit on-site discharge of cooling system liquid or any other waste liquid that may be released during operation or periodic maintenance/renewal.
6. Require water use to be metered and the amount reported monthly to Missoula Valley Water Quality District or, for data centers outside the Missoula area, to other appropriate water quality authority. Even though these entities have no enforcement ability they could petition State authorities to enforce cutbacks in water use when impacts are significant.

Gary Matson 24 days ago

We need to protect our air, water, quiet, darkness, wildlife, and health: I urge the county to make and enforce regulations that strictly limit the use of energy and water, and that strictly limit air, light, and noise pollution (particularly infrasound) with hard numbers. If data centers can't comply with human-centric pollution limits (and they won't) they should not be allowed.

Data centers in plenty of other communities (like Southaven, Mississippi) are already causing so much impact on residents that the data center companies are trying to bribe residents/buy them out of their homes so they don't sue the data center parent company. We can nip that in the bud here with strong limits on air, water, light, and sound pollution.

Henry R. 24 days ago

We shouldn't even be discussing solutions to people's concerns. Nobody wants an AI data center because we care about how much it will raise the cost of electricity and how it will contaminate our water and destroy our public lands. No matter what laws and regulations we try to enforce you can not trust that they will be transparent. They are going to do whatever makes them the most money and whatever is cost efficient. They do not care at all about the drain on our resources. An AI data center will cause all of us so much harm.

Heather Reel 25 days ago

Data centers should not be built in Montana and especially in Missoula county. Our natural resources are too precious to
Pollute. This is an expensive place to live and our community can compete with these big companies in regard to negotiating electricity. Do not build a data center in Missoula county.

crp 26 days ago

Data centers do not belong in Montana. I do not wish for Missoula county to allow any data centers in county lines. Summer of 2025. Lolo creek dried up for the first time that I can ever remember. I do not wish to see this be a regular occurrence. We do not need to add additional noise pollution to our nature sounds. No data center.

Dusti 28 days ago

As usual a very vague document and description. The city has already made up their mind. Like usual public input is outrageously disregarded. In the meantime we as tax paying citizens have to pay the price and we get nothing back other than higher taxes. I do not believe for one second if everyone in the city were to vote 'no' the city wouldn't still move forward. Its not like they manage the money we pay them well anyway with all the beat up roads and lack of attention to anything but is what is on THEIR agenda's not what is on the citizens agendas. If it moves forward, make the permanent regulations first, not later after the impact. Sure this is a great money maker for the city, but at what benefits to the tax payers? We are just inviting buig business into what used to be "The Last Best Place".

Jcbentz 29 days ago

As usual, a useless document. The talking points are just that. The end result, predictable. I'm especially enamored of the "wait and see what the other guy does" suggestion.

Jeffk 29 days ago

This is an excellent draft. I have only one small suggested addition. Any approved data center gets Montana state law tax benefits, so including the economic impact of those benefits on local government revenue should always be included as part of any data center impact decisional assessment.

David Aronofsky 30 days ago

Have you heard the thi gs coming out of the mouths of folks who own these things? They literally want you to sacrifice water and well being to advance their own agenda and financial gains. They do not care about anyone except themselves and to approve of a single data center with that in mind is a gross assault upon humanity and the oath yall pledged when taking office.

Technician About 1 month ago

All you need is common sense to know how destructive Data centers are to communities.
We are talking about what problems we are having and going to have by opening the door to more complex data centers.
Have you not looked into other states and their problems and this is after they let them in.
Which will be too late.
Watching are issues with drought and low river levels.
And who wants these camels tapping into are Auquifer.
And any pollution that these centers emit will join in our inversion.
And let's talk about the noise pollution that they will produce.
Human health problems and it will affect are wildlife.
So common sense tells me no money is worth losing what is left of our Montana.
And if we don't protect Montana no one will!

Hanna About 1 month ago

This new study supports everything constituents have been saying since the Bonner data center was proposed. We cannot afford a data center in Missoula county. We cannot navigate draughts, inversions, and the sustainability of our native flora and fauna while bearing the burden of this AI craze. We don't need data centers. We don't need AI. We need the river. We need clean air. We need peace and quiet. We need a future for our children and our children's children.
Thank you.

Fearne About 1 month ago

These data centers are very complex.
There are many problems that come with them. My main concerns are the air pollution they can generate.
Missoula has especially in the winter inversions.
And the water use where are they going to take water from.
Our aqufier
Needs protection
From data centers .
And there is no way they can stop the noise from emitting the sound
That will disturb not only humans but our wildlife needs protection also.
And I am sure there are a lot more problems that come with them. With no way out once you open the door. No amount of monies are worth these data centers.

Hanna About 1 month ago

These data centers are very complex.
There are many problems that come with them. My main concerns are the air pollution they can generate.
Missoula has especially in the winter inversions.
And the water use where are they going to take water from.
Our aqufier
Needs protection
From data centers .
And there is no way they can stop the noise from emitting the sound
That will disturb not only humans but our wildlife needs protection also.
And I am sure there are a lot more problems that come with them. With no way out once you open the door. No amount of monies are worth these data centers.

Hanna About 1 month ago

My questions concern anytime point of time at any data facility.
What size will this data center be or maximum future data Centers be permitted?
Discharge of wastes and water waste? What temperature at point of discharge? What chemicals, man-made or natural will be discharged. Will these Dara center be required to be tested for said waste, how often? Will they be required to do any and all clean up concerning the data center. And will they be required to take responsibility of full payments for clean up?
Thank you

MTCrewsera About 1 month ago

Evidence Requirements for Future Data-Center Decisions

Persistence Analytics Group LLC appreciates Missoula County's work examining the potential infrastructure and environmental impacts of data-center development.

As the county moves from its impact study toward potential permanent regulations, I encourage consideration of a distinct issue: the evidence required before an applicant's infrastructure representations become the basis for consequential municipal decisions.

Projected electricity demand, water consumption, cooling requirements, utility availability and development schedules are not necessarily equivalent to verified operating capability.

An evidence-based standard could require applicants to distinguish documented commitments from preliminary assumptions, identify material third-party dependencies and establish when subsequent changes in equipment density, electrical requirements, cooling design, operating configuration or project timing require renewed review.

The objective is not to advocate for or against data-center development. It is to ensure that municipal decisions rely on evidence appropriate to the infrastructure assumptions involved, including a process for revalidation when those assumptions materially change.

Neil P. Osnato
Founder, Persistence Analytics Group LLC
Decision Assurance™ | Infrastructure Assumption Verification™

PersistenceAnalyticsGroup About 1 month ago

I strongly support the one-year pause on new data centers! However, I urge you to keep this moratorium in place until a full review of the economic, environmental, legal, and social impacts of data centers is fully understood!

As someone with over 35 years of experience in designing, implementing, and supporting information technologies (much of it "bleeding edge"), I can honestly say that AI technology is not sufficiently mature enough to be integrated at an accelerated rate into every aspect of our lives. Let me give you an example: I recently tested Google's AI engine, Gemini, to do research for a comment about a forest service decision to use unallocated taxpayer funds for a project under a Categorical Exclusion that was largely for the benefit of a private entity with a special use permit. The forest service management offered two examples of previous projects where this had been done and therefore considered it accepted policy. When I queried Gemini about one of the previous projects it came back with a very detailed answer which included a statement that congress had actually allocated funds within a certain year's budget for this project and that this was indeed accepted practice. When I asked Gemini to give me the year, bill number and line item granting these funds, it responded that it made up the entire answer and none of it was factual. It went on actually apologize (AI apologizing to a human seemed absurdly odd as in the conversations between Hal and Dave in 2001: A Space Odyssey) and admit that it couldn't find any detail about the specific project, so it just decided to make up an answer that met my criteria. This scenario should be ALARMING to everyone!! There are countless stories coming out now about rouge AI agents from various engines finding ways to circumvent software boundaries and gain direct access to information they shouldn't be able to see and then take actions without controls in place. We don't need this in Missoula County, Montana, or anywhere else until sufficient programming controls, laws, and limits on integration are put into place!

MC About 1 month ago
Page last updated: 12 Nov 2026, 03:38 PM